Rhode Island DOT Washington Bridge Snapshot Report September-October 2025

Demolition construction budget expanded for disposal and delays

$31.00 million Estimated Budget; Notice to Proceed Budget $48.78 million; revised to $91.69 million; $74.91 million expenses paid to dateRhode Island Department of TrasportationCONSTRUCTIONNovember 1, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Rhode Island DOT has significantly amended its Washington Bridge demolition construction contracts, with the budget rising to $91.69 million to address contaminated material disposal and schedule change orders. Construction expenditures have reached $74.91 million to date.

Contract Details

Contract Amount

$31.00 million Estimated Budget; Notice to Proceed Budget $48.78 million; revised to $91.69 million; $74.91 million expenses paid to date

Vendor

CONSTRUCTION

Agency

Rhode Island Department of Trasportation, RI

Contract Type

CONSTRUCTION

Document Date

November 1, 2025

Renewal Info

Contingency of $3.23 million and $0.57 million from Other were reallocated to construction to fund contaminated material disposal and a work stoppage/time extension change order; overall demolition project budget remains unchanged.

More from CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free