Initial payment for Sylvan Beach Pier reconstruction

$158,555.00LA PORTE AREA WATER AUTHORITYSHIRLEY & SONS CONSTRUCTIONApril 4, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Authority will consider Pay Application No. 1 to Shirley & Sons Construction for $158,555.00 for initial reconstruction work on the Sylvan Beach Pier covering March 9–25, 2026. This payment represents the first draw on a multi‑phase marine construction project budgeted at $1.5 million.

Contract Details

Contract Amount

$158,555.00

Vendor

SHIRLEY & SONS CONSTRUCTION

Agency

LA PORTE AREA WATER AUTHORITY, TX

Contract Type

CONSTRUCTION

Document Date

April 4, 2026

Contract Term

Pay Estimate #1 for work performed 3/9/2026–3/25/2026

Renewal Info

Construction contract progressing via periodic pay estimates; overall pier reconstruction capital budget is $1,500,000 for FY 2025–26.