Shirley & Sons Paid for Progress on Sylvan Beach Pier
Trusted by teams at
Description
The Board will consider approval of Pay Application No. 3 from Shirley & Sons Construction for the Sylvan Beach Pier project, totaling $142,246.92. This payment advances the ongoing construction of the pier started in March 2026.
Contract Details
Contract Amount
$142,246.92
Vendor
SHIRLEY & SONS CONSTRUCTION
Agency
LA PORTE AREA WATER AUTHORITY, TX
Contract Type
CONSTRUCTION
Document Date
June 11, 2026
Contract Term
Work period through May 29, 2026; total contract value $990,000.00; project NTP March 9, 2026, 210 days duration
Renewal Date
2026-10-05
Renewal Info
Progress payment number 3; project has a contract value of $990,000 with anticipated completion after 210 days from March 9, 2026.
More from SHIRLEY & SONS CONSTRUCTION
More from LA PORTE AREA WATER AUTHORITY
La Porte Redevelopment Authority Agenda Packet 2026-06-11
La Porte Redevelopment Authority Agenda Packet 2026-06-11
La Porte Redevelopment Authority Agenda Packet 2026-06-11
La Porte Redevelopment Authority Agenda Packet 2026-06-11
La Porte Redevelopment Authority Agenda Packet 2026-06-11
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.