SUN Trail construction contract amended for added work
Trusted by teams at
Description
The City of Port Orange is processing Change Order No. 1 with Masci General Contractor, Inc. for the St. John's River to Sea Loop SUN Trail Project, adding up to $37,731.77 and extending the contract by 17 days. The amendment covers design adjustments, drainage revisions, tree removals, and replacement of a damaged shared-use path segment, bringing the total contract value to $1,671,593.42 with final completion now scheduled for July 27, 2026.
Contract Details
Contract Amount
Additional amount not to exceed $37,731.77; revised total contract amount $1,671,593.42
Vendor
MASCI GENERAL CONTRACTOR INC
Agency
City of Port Orange, FL
Contract Type
CONSTRUCTION
Document Date
April 6, 2026
Contract Term
Contract time extended by 17 days; new final completion date July 27, 2026
Renewal Date
2026-07-27
Renewal Info
Change Order No. 1 amends the August 19, 2025 EJCDC construction agreement under ITB 25-13, increasing the contract sum by $37,731.77 (within a previously approved $80,000 contingency) and extending contract time from 270 to 287 days; substantial completion shifts from June 16, 2026 to July 3, 2026 and final completion from July 10, 2026 to July 27, 2026.
More from MASCI GENERAL CONTRACTOR INC
More from City of Port Orange
City of Port Orange Fire and Rescue Pension Board of Trustees Quarterly Meeting Agenda 2026-05-26
City of Port Orange Fire and Rescue Pension Board of Trustees Quarterly Meeting Agenda 2026-05-26
City of Port Orange Fire and Rescue Pension Board of Trustees Quarterly Meeting Agenda 2026-05-26
City of Port Orange Fire and Rescue Pension Board of Trustees Quarterly Meeting Agenda 2026-05-26
City of Port Orange Fire and Rescue Pension Board of Trustees Quarterly Meeting Agenda 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.