CONSTRUCTIONAMENDED

Change Order Expands TK Construction Bloomington Contract

West Valley Water District is considering approval of Construction Change Order No. 2 with Kirtley Construction Inc. dba TK Construction for the Bloomington Alleyway Water Main Replacement Project – Phase 3C, adding $322,430.32 and 10 working days to handle unforeseen utility conflicts and customer-side modifications. The change brings the total contract amount to $5,256,862.64 with completion now scheduled for October 28, 2026.

Status
AMENDED
Document date
April 16, 2026
Contract type
CONSTRUCTION
Vendor
Kirtley Construction Inc Dba Tk Construction
Agency
West Valley Water District · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$322,430.32 change order (new total contract value $5,256,862.64)
Contract type
CONSTRUCTION
Contract term
Contract time increased by 10 working days to a total of 258 working days; new completion date October 28, 2026
Renewal date
2026-10-28
Renewal
Second change order to the August 19, 2025 construction agreement; prior Change Order No. 1 added $75,000 and 8 days. This amendment includes both lump-sum and time-and-materials components, with further changes requiring additional Board approval.
Document type
AgendaPacket
Source document
West Valley Water District Board Meeting Agenda Packet April 2026

Related contracts

Other contracts from Kirtley Construction Inc Dba Tk Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by West Valley Water District?

Kirtley Construction Inc Dba Tk Construction was awarded this construction contract by West Valley Water District, as recorded on April 16, 2026. The contract value is $322,430.32 change order (new total contract value $5,256,862.64).

How much is the Kirtley Construction Inc Dba Tk Construction contract with West Valley Water District worth?

The Kirtley Construction Inc Dba Tk Construction contract with West Valley Water District is valued at $322,430.32 change order (new total contract value $5,256,862.64), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in West Valley Water District Board Meeting Agenda Packet April 2026 (AgendaPacket), dated April 16, 2026 from West Valley Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Kirtley Construction Inc Dba Tk Construction hold?

Kirtley Construction Inc Dba Tk Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Kirtley Construction Inc Dba Tk Construction's profile

What is West Valley Water District currently buying?

Explore West Valley Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View West Valley Water District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free