CONSTRUCTIONAMENDED

Change Order Expands Scope for Bloomington Phase 3C Waterline

West Valley Water District approved Construction Change Order No. 2 with Kirtley Construction, Inc. dba TK Construction for the Bloomington Alleyway Water Main Replacement Project – Phase 3C, increasing the contract by $322,430.32 and extending the schedule by 10 working days. The amendment funds work to avoid unforeseen utility conflicts and complete additional customer-side service modifications.

Status
AMENDED
Document date
April 16, 2026
Contract type
CONSTRUCTION
Vendor
Kirtley Construction Inc Dba Tk Construction
Agency
West Valley Water Dist · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$322,430.32 (change order increase), new total contract value $5,256,862.64
Contract type
CONSTRUCTION
Contract term
Contract time increased by 10 working days to a total of 258 working days; revised completion date October 28, 2026
Renewal date
2026-10-28
Renewal
Second change order to the August 19, 2025 construction contract; prior Change Order No. 1 added $75,000 and 8 days. This amendment further increases price and time to resolve additional field conditions.
Document type
Agenda
Source document
West Valley Water District Board Meeting Agenda April 2026

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by West Valley Water Dist?

Kirtley Construction Inc Dba Tk Construction was awarded this construction contract by West Valley Water Dist, as recorded on April 16, 2026. The contract value is $322,430.32 (change order increase), new total contract value $5,256,862.64.

How much is the Kirtley Construction Inc Dba Tk Construction contract with West Valley Water Dist worth?

The Kirtley Construction Inc Dba Tk Construction contract with West Valley Water Dist is valued at $322,430.32 (change order increase), new total contract value $5,256,862.64, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in West Valley Water District Board Meeting Agenda April 2026 (Agenda), dated April 16, 2026 from West Valley Water Dist. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Kirtley Construction Inc Dba Tk Construction hold?

Kirtley Construction Inc Dba Tk Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Kirtley Construction Inc Dba Tk Construction's profile

What is West Valley Water Dist currently buying?

Explore West Valley Water Dist's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View West Valley Water Dist's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free