Clyde G. Steagall Wins Gridley Generator Contract
Trusted by teams at
Description
The Housing Authority awarded Clyde G. Steagall, Inc. a $257,848 construction contract for the Gridley Farm Labor Housing Generator Project, supported by a total project budget of $492,066 with contingency. The project will install a stationary natural gas emergency generator and automatic transfer switch, with substantial completion required within 300 days of a Notice to Proceed issued by May 4, 2026.
Contract Details
Contract Amount
$257,848 (construction bid); total project budget $492,066 including contingency and engineering
Vendor
CLYDE G. STEAGALL INC
Agency
county OF BUTTE HSG AUTH, CA
Contract Type
CONSTRUCTION
Document Date
April 16, 2026
Contract Term
300-day contractual period for substantial completion from Notice to Proceed issued no later than May 4, 2026
Renewal Date
2027-02-28
Renewal Info
Initial construction contract authorized by Resolution 4990; project includes a 300-day substantial completion requirement from issuance of Notice to Proceed and is funded through the State backup generator program with contingency for delays.
More from CLYDE G. STEAGALL INC
More from county OF BUTTE HSG AUTH
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Board of Commissioners Meeting Agenda 2026-05-21
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.