Gridley Generator Construction Awarded to Clyde G. Steagall
Trusted by teams at
Description
The Housing Authority of the County of Butte awarded a construction contract to Clyde G. Steagall, Inc. for $257,848 to build a new natural gas emergency generator and automatic transfer switch at the Gridley Farm Labor Housing well site. The work, funded under a $492,066 State Water Board project budget, must reach substantial completion within 300 days of a Notice to Proceed issued by May 4, 2026.
Contract Details
Contract Amount
$257,848 (construction bid); total project budget $492,066 including 10% contingency
Vendor
CLYDE G. STEAGALL INC
Agency
county OF BUTTE HSG AUTH, CA
Contract Type
CONSTRUCTION
Document Date
May 21, 2026
Contract Term
300-day contractual period for substantial completion from Notice to Proceed (to be issued no later than May 4, 2026)
Renewal Date
2027-02-28
Renewal Info
Single 300-day construction contract; any delay beyond February 28, 2027 could require HACB to use the property’s construction reserve if RCAC’s program agreement is not extended.
More from CLYDE G. STEAGALL INC
More from county OF BUTTE HSG AUTH
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Housing Authority of the County of Butte Board of Commissioners Meeting Agenda 2026-05-21
Housing Authority of the County of Butte Agenda Packet 2026-05-21
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.