Ione wastewater construction contract continues with payment 12
Trusted by teams at
Description
The City of Ione is progressing with its Wastewater System Improvements - 2024 construction contract with Swaggart Brothers Inc., originally valued at $8,378,708.00 and now adjusted to $7,681,726.37 after change orders. Application for Payment No. 12 dated September 30, 2025 reflects $4,342,758.10 in completed work and stored materials and a current payment due of $245,069.38.
Contract Details
Contract Amount
$8,378,708.00 (original); Net change by change orders ($696,981.63); Current contract price $7,681,726.37
Vendor
SWAGGART BROTHERS INC
Agency
City of Ione, OR
Contract Type
CONSTRUCTION
Document Date
September 18, 2025
Renewal Info
Multiple change orders have reduced the original contract price by $696,981.63 to a current value of $7,681,726.37. Future applications for payment will continue until project completion; no explicit renewal or extension terms are stated in the excerpt.
More from SWAGGART BROTHERS INC
More from City of Ione
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.