City Extends Sewer Project Contract Time with No Added Cost
Trusted by teams at
Description
Ione approved Change Order No. 14 with Swaggart Brothers Inc. to extend the Wastewater System Improvements contract time by 84 days at no additional cost. The adjustment moves substantial completion to July 16, 2026, with final payment expected by August 15, 2026.
Contract Details
Contract Amount
$7,730,602.83 (no change under CO 14)
Vendor
SWAGGART BROTHERS INC
Agency
City of Ione, OR
Contract Type
CONSTRUCTION
Document Date
May 12, 2026
Contract Term
Contract time extended 84 days; Substantial Completion moved from April 23, 2026 to July 16, 2026; Final Payment moved from May 23, 2026 to August 15, 2026
Renewal Date
2026-08-15
Renewal Info
CO 14 extends the construction contract time by 84 days, revising substantial completion to July 16, 2026 and final payment to August 15, 2026, with no change in contract price.
More from SWAGGART BROTHERS INC
More from City of Ione
City of Ione Agenda Packet 2026-05-12
City of Ione Agenda Packet 2026-05-12
Ione City Council Agenda 2026-05-12
Ione City Council Agenda 2026-05-12
Ione City Council Agenda 2026-05-12
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.