Brighton Central School District 2023 Capital Improvement Project Phase 2 Monthly Progress Report March 2026

Major Sitework Contract with DiFiore Construction Ongoing

$8,730,000Brighton Central School DistrictDIFIORE CONSTRUCTIONMarch 31, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

DiFiore Construction continues sitework under Contract 205 for the Brighton Central School District’s 2023 Capital Improvement Project, maintaining an $8,730,000 contract value. Work includes site coverage and planned testing and adjustments for athletic fields and French Road site improvements.

Contract Details

Contract Amount

$8,730,000

Vendor

DIFIORE CONSTRUCTION

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

March 31, 2026

Contract Term

Phase 2 – Contract 205 Sitework scope, approximately Dec 1, 2025 to Aug 31, 2027

Renewal Info

Several DiFiore-related issues are open and may lead to change orders or credits, including temporary facilities removal, sitework scope credits, additional crusher run, sitework testing, and storm drain and laydown area work.