PSE Utility Relocation Agreement for SR 516 Project
Trusted by teams at
Description
Covington plans to enter a Facility Relocation Agreement with Puget Sound Energy, Inc. to relocate electric facilities for the SR 516 (Jenkins Creek–185th Ave SE) Widening culvert project, with city-paid costs estimated at $133,993.61. The agreement sets schedule and reimbursement terms for temporary overhead and permanent underground power line relocations.
Contract Details
Contract Amount
Estimated $133,993.61 (actual relocation costs to be reimbursed)
Vendor
PUGET SOUND ENERGY INC
Agency
City of Covington, WA
Contract Type
UTILITIES
Document Date
June 23, 2026
Contract Term
Relocation Agreement dated May 27, 2026; Relocation Schedule shows temporary relocation June 24–25 and permanent underground conduit installation August 17–18 (year implied 2026)
Renewal Info
Agreement reimburses PSE for actual relocation costs beyond the estimate; PSE may suspend work or terminate if costs exceed the estimate by more than 20% without city acceptance. No automatic renewals; termination provisions cover incomplete work.
More from PUGET SOUND ENERGY INC
More from City of Covington
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.