PSE Utility Relocation Agreement for SR 516 Culvert
Trusted by teams at
Description
Covington City Council is asked to approve a Facility Relocation Agreement with Puget Sound Energy, Inc. to relocate electric facilities for the SR 516 widening culvert work, with relocation costs estimated at $133,993.61 reimbursed by the City. The agreement, dated May 27, 2026, schedules temporary relocation in June and permanent underground conduit work in August 2026.
Contract Details
Contract Amount
Estimated $133,993.61 (City to reimburse actual costs)
Vendor
PUGET SOUND ENERGY INC
Agency
City of Covington, WA
Contract Type
UTILITIES
Document Date
June 23, 2026
Contract Term
Relocation work per Exhibit C: temporary pole relocate June 24–25, 2026 and permanent UG conduit installation August 17–18, 2026; agreement dated May 27, 2026
Renewal Info
Single-project utility facility relocation agreement tied to the SR 516 widening culvert work; no renewal or extension terms are specified. Additional costs above the estimate require City approval and payment under the agreement.
More from PUGET SOUND ENERGY INC
More from City of Covington
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.