Phase 2 Pump Station Contract Amended with Seven Valleys
Trusted by teams at
Description
Seven Valleys Concrete’s CMAR contract for Phase 2 of the pump station was amended to $12,129,372. Work is in progress with substantial completion by December 2025 and final completion in January 2026.
Contract Details
Contract Amount
$12,129,372.00
Vendor
SEVEN VALLEYS CONCRETE
Agency
Benton-Washington Regional Public Water Authority, AR
Contract Type
CONSTRUCTION
Document Date
January 22, 2026
Contract Term
430 calendar days (November 25, 2024 – December 30, 2025 substantial, January 29, 2026 final)
Renewal Date
2026-01-29
Renewal Info
GMP amended by Change Order. No explicit renewal; construction-phase to completion.
More from SEVEN VALLEYS CONCRETE
Issuing Agency
Special District
Rogers, AR
More from Benton-Washington Regional Public Water Authority
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.