Seven Valleys CMAR Contract Progresses for Pump Station
Trusted by teams at
Description
The Authority continues work with Seven Valleys Concrete as the CMAR contractor for Phase 1 of the High Service Pump Station and Electrical Upgrades. The project’s GMP is $6.8 million, with substantial completion expected March 2025 and final by December 2025. Over $6.1 million has been paid as of January 2026.
Contract Details
Contract Amount
$6,800,000.00
Vendor
SEVEN VALLEYS CONCRETE
Agency
Benton-Washington Regional Public Water Authority, AR
Contract Type
CONSTRUCTION
Document Date
January 22, 2026
Contract Term
295 calendar days (June 10, 2024 – March 1, 2025 substantial, December 30, 2025 final)
Renewal Date
2025-12-30
Renewal Info
CMAR with GMP. No explicit renewal; contract to completion of construction milestones.
More from SEVEN VALLEYS CONCRETE
Issuing Agency
Special District
Rogers, AR
More from Benton-Washington Regional Public Water Authority
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Benton/Washington Regional Public Water Authority Board Meeting Minutes January 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.