Austin adds contingency to Northwest Lift Station contract
Trusted by teams at
Description
The City of Austin is considering approval of additional contingency funding of $537,225 for the construction contract with Santa Clara Construction, LTD for the Northwest Lift Station Improvements: Rock Harbor Force Main and Four Points #2, bringing the total not-to-exceed amount to $5,280,171. The added funds address increased traffic control plan costs and redesign needs arising from field condition discrepancies.
Contract Details
Contract Amount
Increase by $537,225 for a total amount not to exceed $5,280,171
Vendor
SANTA CLARA CONSTRUCTION LTD
Agency
Austin Water, TX
Contract Type
CONSTRUCTION
Document Date
May 20, 2026
Renewal Info
Original construction contract and 10% contingency were approved by Council on February 13, 2025, with subsequent administrative authority funds and multiple change orders. The May 28, 2026 action would authorize CO#7 and additional contingency, increasing total contract authorization to $5,280,171.
More from SANTA CLARA CONSTRUCTION LTD
More from Austin Water
Austin Water StaffReport Crosstown Tunnel Centralized Odor Control Facility Project 2026-05-20
Austin Water StaffReport Crosstown Tunnel Centralized Odor Control Facility Project 2026-05-20
Austin Water StaffReport Crosstown Tunnel Centralized Odor Control Facility Project 2026-05-20
Austin Water StaffReport Hyde Park Water and Wastewater Pipeline Renewal Project Change Order 2026-05-20
City of Austin StaffReport Interlocal Agreement with Austin Transit Partnership 2026-05-28
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.