Hyde Park pipeline change order to Santa Clara Construction
Trusted by teams at
Description
Austin Water seeks Council approval of Change Order No. 5 with Santa Clara Construction Ltd. for $831,153 to fund additional water utility and temporary service work on the Hyde Park Water and Wastewater Pipeline Renewal Project, bringing the contract total to $9,392,249. Funding is provided from Austin Water’s Capital Budget and reflects added scope due to unforeseen field conditions and additional infrastructure needs.
Contract Details
Contract Amount
$831,153 (total contract not to exceed $9,392,249)
Vendor
SANTA CLARA CONSTRUCTION LTD
Agency
Austin Water, TX
Contract Type
CONSTRUCTION
Document Date
May 20, 2026
Renewal Info
Original construction contract of $7,722,797.50 was approved by Council on December 9, 2021 with a 10% contingency of $772,297.75 and subsequent administrative authority of $66,000. Prior change orders (CO #1–#4) totaling $756,370 increased the contract by 9.8%; proposed CO #5 adds $831,153, resulting in a cumulative change of approximately 21.6% and a new not-to-exceed total of $9,392,249. Council authorization of additional contingency funding allows future change orders within the approved contingency amount.
More from SANTA CLARA CONSTRUCTION LTD
More from Austin Water
Austin Water StaffReport Crosstown Tunnel Centralized Odor Control Facility Project 2026-05-20
Austin Water StaffReport Crosstown Tunnel Centralized Odor Control Facility Project 2026-05-20
Austin Water StaffReport Crosstown Tunnel Centralized Odor Control Facility Project 2026-05-20
City of Austin StaffReport Interlocal Agreement with Austin Transit Partnership 2026-05-28
City of Austin StaffReport Interlocal Agreement with Austin Transit Partnership 2026-05-28