Change Order Lowers Cost of Oak Grove Park Pavilion
Trusted by teams at
Description
Ascension Parish proposes Change Order No. 1 with Dantin Custom Homes, LLC dba Dantin Builders for the Oak Grove Park pavilion project, reducing the contract by $21,400. The adjustment lowers the total construction price to $111,150 while keeping the existing 120-day schedule intact.
Contract Details
Contract Amount
Decrease of $21,400.00 for new total contract price of $111,150.00
Vendor
DANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERS
Agency
Ascension Parish Fire District #2, LA
Contract Type
CONSTRUCTION
Document Date
May 9, 2026
Contract Term
120 days; Substantial Completion 09/02/2026; Final Payment 10/17/2026
Renewal Date
2026-10-17
Renewal Info
First change order to Parish Contract No. 260136, revising the contract price downward while maintaining the original 120-day completion period and milestone dates.
More from DANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERS
More from Ascension Parish Fire District #2
Ascension Parish Planning Commission Meeting Agenda May 2026
Ascension Parish Planning Commission Meeting Agenda May 2026
Ascension Parish Planning Commission Meeting Agenda May 2026
Ascension Parish Planning Commission Meeting Agenda May 2026
Ascension Parish Planning Commission Meeting Agenda May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.