Change Order Lowers Cost of Oak Grove Park Pavilion
Trusted by teams at
Description
Ascension Parish plans to approve Change Order No. 1 with Dantin Custom Homes LLC dba Dantin Builders for the Oak Grove Park pavilion, reducing the contract amount by $21,400 to $111,150. The deduction reflects savings in foundation and electrical work with no extension of the 120-day schedule.
Contract Details
Contract Amount
Decrease of $21,400.00; new total contract amount $111,150.00
Vendor
DANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERS
Agency
Ascension Parish Section 8 Program, LA
Contract Type
CONSTRUCTION
Document Date
May 12, 2026
Contract Term
120 days; Substantial Completion 09/02/2026; Final payment 10/17/2026
Renewal Date
2026-10-17
Renewal Info
First change order to construction Contract No. 260136; reduces price but leaves contract time and completion dates unchanged.
More from DANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERS
Issuing Agency
Local Housing Authority
Donaldsonville, LA
More from Ascension Parish Section 8 Program
Parish of Ascension Finance Committee Meeting Agenda May 2026
Parish of Ascension Finance Committee Meeting Agenda May 2026
Parish of Ascension Finance Committee Meeting Agenda May 2026
Parish of Ascension Finance Committee Meeting Agenda May 2026
Parish of Ascension Finance Committee Meeting Agenda May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.