Parish of Ascension Finance Committee Meeting Agenda Packet May 2026

Change Order Lowers Cost of Oak Grove Park Pavilion

Decrease of $21,400.00; new total contract amount $111,150.00Ascension Parish Section 8 ProgramDANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERSMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Ascension Parish plans to approve Change Order No. 1 with Dantin Custom Homes LLC dba Dantin Builders for the Oak Grove Park pavilion, reducing the contract amount by $21,400 to $111,150. The deduction reflects savings in foundation and electrical work with no extension of the 120-day schedule.

Contract Details

Contract Amount

Decrease of $21,400.00; new total contract amount $111,150.00

Vendor

DANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERS

Agency

Ascension Parish Section 8 Program, LA

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Contract Term

120 days; Substantial Completion 09/02/2026; Final payment 10/17/2026

Renewal Date

2026-10-17

Renewal Info

First change order to construction Contract No. 260136; reduces price but leaves contract time and completion dates unchanged.

More from DANTIN CUSTOM HOMES LLC DBA DANTIN BUILDERS

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free