Civic IQ
CONSTRUCTIONRATIFIED

florida_keys_aqueduct_authority_board_meeting_agen.pdf

Plantation Key Main Contract Reduced, Pipe Purchased Directly

Contract reduced from $56,966,790 to $51,708,587; Owner Direct Purchase $5,181,188Florida Keys Aqueduct AuthorityMICHELS PIPELINE INCAugust 5, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board ratified a deductive change order with Michels Pipeline, Inc. on the Plantation Key Transmission Main project, cutting the contract from $56.97 million to $51.71 million and authorizing a $5.18 million owner direct purchase of steel pipe.

Contract Details

Contract Amount

Contract reduced from $56,966,790 to $51,708,587; Owner Direct Purchase $5,181,188

Vendor

MICHELS PIPELINE INC

Agency

Florida Keys Aqueduct Authority, FL

Contract Type

CONSTRUCTION

Document Date

August 5, 2025

Renewal Info

Deductive Change Order No. 1 restructures project costs and lowers the contractor’s contract amount while shifting steel pipe procurement to owner direct purchase.

More from MICHELS PIPELINE INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free