HVAC and Mechanical Upgrade Contract Duration Extended
Trusted by teams at
Description
The SFPUC extended the duration contingency on Contract WW-543 with Cal State Constructors, Inc. to 1,478 days to address equipment and work delays at the Southeast Water Pollution Control Plant, with no cost change.
Contract Details
Contract Amount
No change to contract amount
Vendor
CAL STATE CONSTRUCTORS INC
Agency
San Francisco Public Utilities Commission, CA
Contract Type
CONSTRUCTION
Document Date
May 27, 2026
Contract Term
Revised duration limit of 1,478 calendar days (approximately four years and one month)
Renewal Info
Duration contingency increased by 389 days; cost unchanged.
More from CAL STATE CONSTRUCTORS INC
Issuing Agency
Special District
San Francisco, CA
More from San Francisco Public Utilities Commission
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.