San Francisco Public Utilities Commission Regular Meeting Agenda Feb 2026

Cal State Constructors Gets Extension for Plant Upgrades

San Francisco Public Utilities CommissionCAL STATE CONSTRUCTORS INCFebruary 24, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Commission approved a 389-day extension for Cal State Constructors, Inc. to complete HVAC and mechanical upgrades at the Southeast Water Pollution Control Plant.

Contract Details

Vendor

CAL STATE CONSTRUCTORS INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

February 24, 2026

Contract Term

Revised duration limit of 1,478 calendar days (approx. 4 years and 1 month)

Renewal Info

Duration contingency increased; now totals 1,478 calendar days.