San Francisco Bay Area Water Emergency Transportation Authority Minutes of the Board of Directors Meeting 2026-04-09

Board Approves SFPUC Agreement For Ferry Terminal Power

Engineering advance payment of approximately $1,116,800 toward an estimated $5,584,000 preliminary front-of-meter cost and approximately $10,000,000 total front-of-meter costSan Francisco Bay Area Water Emergency Transportation AuthoritySAN FRANCISCO PUBLIC UTILITIES COMMISSIONApril 9, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The WETA Board approved an agreement with the San Francisco Public Utilities Commission to secure electric service for the Downtown San Francisco ferry terminal, including an engineering advance payment of about $1.1 million toward an eventual front-of-meter cost estimated at $10 million. The action reserves a dedicated 10‑megawatt service line needed to power WETA’s new battery-electric ferry fleet.

Contract Details

Contract Amount

Engineering advance payment of approximately $1,116,800 toward an estimated $5,584,000 preliminary front-of-meter cost and approximately $10,000,000 total front-of-meter cost

Vendor

SAN FRANCISCO PUBLIC UTILITIES COMMISSION

Agency

San Francisco Bay Area Water Emergency Transportation Authority, CA

Contract Type

UTILITIES

Document Date

April 9, 2026

Renewal Info

One-time agreement to secure and fund a dedicated 10‑megawatt electric service line; a second advance payment and later construction phases will return to the Board for approval. Deposit is refundable minus design costs if the project is canceled.

More from SAN FRANCISCO PUBLIC UTILITIES COMMISSION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free