Frederick Water Awards Construction Contract to Burns & Mcdonnell (May 2026)

Frederick Water approved a design-build Guaranteed Maximum Price (GMP 1) contract with Burns & McDonnell for $28,813,728 to construct the water supply phase of the East Pit Advanced Treatment Project, including intake, pump station, and pipelines. Total authorized funding for this phase, including owner-controlled contingency, is $33,056,620, with substantial completion required by December 28, 2027 and final completion by February 25, 2028.

Status
APPROVED
Document date
May 12, 2026
Contract type
CONSTRUCTION
Vendor
Burns & Mcdonnell
Agency
Frederick Water · VA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$28,813,728 (GMP 1); total authorized project funding for this phase including Owner-controlled contingency: $33,056,620
Contract type
CONSTRUCTION
Contract term
Substantial Completion by December 28, 2027; Final Completion by February 25, 2028; one-year warranty on the pump station
Renewal date
2028-02-25
Renewal
GMP 1 covers the water supply phase with defined substantial and final completion dates and liquidated damages; future project work will proceed under a separate GMP 2 contract expected for consideration in September 2026. No explicit renewal options are described for this GMP 1 contract.
Document type
Minutes
Source document
Frederick Water Minutes Special Meeting May 12, 2026

Related contracts

Other contracts from Burns & Mcdonnell.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Frederick Water?

Burns & Mcdonnell was awarded this construction contract by Frederick Water, as recorded on May 12, 2026. The contract value is $28,813,728 (GMP 1); total authorized project funding for this phase including Owner-controlled contingency: $33,056,620.

How much is the Burns & Mcdonnell contract with Frederick Water worth?

The Burns & Mcdonnell contract with Frederick Water is valued at $28,813,728 (GMP 1); total authorized project funding for this phase including Owner-controlled contingency: $33,056,620, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Frederick Water Minutes Special Meeting May 12, 2026 (Minutes), dated May 12, 2026 from Frederick Water. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Burns & Mcdonnell hold?

Burns & Mcdonnell may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Burns & Mcdonnell's profile

What is Frederick Water currently buying?

Explore Frederick Water's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Frederick Water's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free