Brighton Central School District 2023 Capital Improvement Project Phase 2 Report January 2026

Plumbing upgrades by Nairy Mechanical in boiler room

Brighton Central School DistrictNAIRY MECHANICALJanuary 30, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Nairy Mechanical, under Plumbing Contract 203, advanced plumbing upgrades in the Brighton High School boiler room during January 2026. Work included removal of domestic hot water equipment, slab modifications for sump pumps, and pouring a new pad for the domestic hot water plant.

Contract Details

Vendor

NAIRY MECHANICAL

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

January 30, 2026

Contract Term

Brighton 2023 Phase 2 Capital Improvement Project, approximately December 1, 2025 – August 31, 2027

Renewal Date

2027-08-31

Renewal Info

Plumbing scope under Contract 203 within the 2023 Phase 2 Capital Improvement Project; no renewal options noted in the report.

More from NAIRY MECHANICAL

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free