Brighton Central School District 2023 Capital Improvement Project Phase 2 Monthly Progress Report March 2026

Plumbing Contract with Nairy Mechanical Amended

$661,989Brighton Central School DistrictNAIRY MECHANICALMarch 31, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Nairy Mechanical continues plumbing work under Contract 203 at Brighton High School, with the contract value revised to $661,989 after a $4,289 change order for unforeseen double slab conditions. The contractor is installing new domestic hot water piping and sump pump lines in the boiler room.

Contract Details

Contract Amount

$661,989

Vendor

NAIRY MECHANICAL

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

March 31, 2026

Contract Term

Phase 2 – Contract 203 Plumbing scope, approximately Dec 1, 2025 to Aug 31, 2027

Renewal Info

Change Order 203-001, issued March 27, 2026, added $4,289 for remediation of an unforeseen double slab in the boiler room storage room.

More from NAIRY MECHANICAL

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free