City of Holland AgendaPacket 2026-05-20

Newkirk Electric Recommended for James Street Breaker Project

$201,642 (base $183,642 plus $18,000 contingency)City of Holland cityNEWKIRK ELECTRIC INCMay 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Holland Board of Public Works recommended a $201,642 construction contract with Newkirk Electric Inc. to replace three 138kV breakers at the James Street Substation, supported by a $145,860 FY 2026 capital budget amendment bringing the project budget to $595,860. Newkirk submitted the lowest evaluated bid among three qualified contractors.

Contract Details

Contract Amount

$201,642 (base $183,642 plus $18,000 contingency)

Vendor

NEWKIRK ELECTRIC INC

Agency

City of Holland city, MI

Contract Type

CONSTRUCTION

Document Date

May 20, 2026

Contract Term

Work to start on or before October 12, 2026; approximately 4 weeks duration

Renewal Date

2026-11-15

More from NEWKIRK ELECTRIC INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free