Newkirk Electric Recommended for Substation Project
Trusted by teams at
Description
Holland Board of Public Works recommended a $201,642 construction contract with Newkirk Electric Inc. to replace three 138kV breakers at the James Street Substation, along with a $145,860 FY 2026 capital budget amendment for a total project budget of $595,860. The agreement is pending City Attorney approval and anticipated to start in October 2026.
Contract Details
Contract Amount
$183,642 plus 10% contingency of $18,000 (total $201,642)
Vendor
NEWKIRK ELECTRIC INC
Agency
City of Holland city, MI
Contract Type
CONSTRUCTION
Document Date
May 18, 2026
Contract Term
Project work planned for approximately four weeks beginning October 12, 2026
More from NEWKIRK ELECTRIC INC
More from City of Holland city
City of Holland Human Relations Commission Agenda Packet 2026-06-18
City of Holland Downtown Design Review Board Agenda Packet 2026-06-15
City of Holland Downtown Design Review Board Agenda Packet 2026-06-15
City of Holland Downtown Design Review Board Agenda May 2026
City of Holland City Council Meeting Agenda Packet May 20 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.