SFPUC Regular Meeting Agenda April 28, 2026

Sunol Valley Chloramination Facility Contract Contingency Increase

Revised cost limit of $12,283,350 (increase of $2,000,000 to contingency)San Francisco Public Utilities CommissionANVIL BUILDERS INCApril 28, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The SFPUC will amend Contract No. WD-2893 with Anvil Builders, Inc., adding $2,000,000 in contingency and 700 days to reach a cost limit of $12,283,350 and 1,426 days. The extension supports design changes to control systems and updated shutdown scheduling for the Sunol Valley Chloramination Facility.

Contract Details

Contract Amount

Revised cost limit of $12,283,350 (increase of $2,000,000 to contingency)

Vendor

ANVIL BUILDERS INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

April 28, 2026

Contract Term

Revised duration limit of 1,426 consecutive calendar days (approximately 3 years and 10 months)

Renewal Info

Contract No. WD-2893 is amended to increase both cost and duration contingencies; the revised cost limit is $12,283,350 and the revised duration limit is 1,426 days.

More from ANVIL BUILDERS INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free