SFPUC Regular Meeting Agenda April 28, 2026

Channel Force Main Intertie Contract Contingency Increase

Revised cost limit of $22,175,899 (increase of $2,800,000 to existing contingency)San Francisco Public Utilities CommissionANVIL BUILDERS INCApril 28, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The SFPUC will amend Contract No. WW-723R with Anvil Builders Inc., adding $2,800,000 in contingency and 243 days to reach a cost limit of $22,175,899 and 1,374 days. The changes address unforeseen pipe conditions and extend dry-weather construction for the Channel Force Main Intertie into 2026.

Contract Details

Contract Amount

Revised cost limit of $22,175,899 (increase of $2,800,000 to existing contingency)

Vendor

ANVIL BUILDERS INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

April 28, 2026

Contract Term

Revised duration limit of 1,374 consecutive calendar days

Renewal Info

Contract No. WW-723R is amended to increase both cost and duration contingencies, bringing the total cost limit to $22,175,899 and total duration to 1,374 days.

More from ANVIL BUILDERS INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free