Channel Force Main Intertie Contract Contingency Increase
Trusted by teams at
Description
The SFPUC will amend Contract No. WW-723R with Anvil Builders Inc., adding $2,800,000 in contingency and 243 days to reach a cost limit of $22,175,899 and 1,374 days. The changes address unforeseen pipe conditions and extend dry-weather construction for the Channel Force Main Intertie into 2026.
Contract Details
Contract Amount
Revised cost limit of $22,175,899 (increase of $2,800,000 to existing contingency)
Vendor
ANVIL BUILDERS INC
Agency
San Francisco Public Utilities Commission, CA
Contract Type
CONSTRUCTION
Document Date
April 28, 2026
Contract Term
Revised duration limit of 1,374 consecutive calendar days
Renewal Info
Contract No. WW-723R is amended to increase both cost and duration contingencies, bringing the total cost limit to $22,175,899 and total duration to 1,374 days.
More from ANVIL BUILDERS INC
Issuing Agency
Special District
San Francisco, CA
More from San Francisco Public Utilities Commission
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.