Pay Application Approved for WWTF Upgrade Work
Trusted by teams at
Description
The Avoca Village Board approved Pay Application #7 to MZ Construction for $76,000.00 as part of the 2024 wastewater treatment facility upgrade project. The payment continues funding under the existing construction contract for the WWTF improvements.
Contract Details
Contract Amount
$76,000.00
Vendor
MZ CONSTRUCTION
Agency
Avoca village, WI
Contract Type
CONSTRUCTION
Document Date
January 12, 2026
Renewal Info
Progress payment under an ongoing construction contract for the 2024 WWTF upgrade; amendment or final completion details not provided.