Civic IQ
CONSTRUCTIONONGOING

Town of Huntington Water and Sewer Meeting Agenda 2026-05-06

Western Earth Works Continues 51 Basket Street Water Line Work

$95,251.54Town of HuntingtonWESTERN EARTH WORKSMay 6, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Western Earth Works continued work on the 51 Basket Street temporary water line, repairing leaks and testing connections, with an invoice of $95,251.54 processed. Further pressure and bacteriological testing are required before connecting the line to 51 Basket Street.

Contract Details

Contract Amount

$95,251.54

Vendor

WESTERN EARTH WORKS

Agency

Town of Huntington, MA

Contract Type

CONSTRUCTION

Document Date

May 6, 2026

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free