Town of Huntington Water and Sewer Meeting Minutes April 2026

Western Earth Works Paid for 51 Basket Street Work

$95,251.54Town of HuntingtonWESTERN EARTH WORKSApril 1, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Western Earth Works continued work on the 51 Basket Street temporary water line project, repairing leaks and testing connections, and submitted a $95,251.54 invoice that has been processed by the town. The project is funded through a DEP contract with reimbursement expected after payment.

Contract Details

Contract Amount

$95,251.54

Vendor

WESTERN EARTH WORKS

Agency

Town of Huntington, MA

Contract Type

CONSTRUCTION

Document Date

April 1, 2026