Fremont City Council Meeting Agenda April 14, 2026

Central Park Restroom Contract Amendment with Alex Kushner General

Additional $80,000; total contract amount not to exceed $1,032,200City of FremontALEX KUSHNER GENERAL INCApril 14, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Fremont plans to amend its construction contract with Alex Kushner General, Inc. for the Central Park Restroom Replacement Project by adding $80,000, raising the total not-to-exceed amount to $1,032,200. The additional funding will cover extra work on the replacement of existing restroom facilities, which is exempt from CEQA.

Contract Details

Contract Amount

Additional $80,000; total contract amount not to exceed $1,032,200

Vendor

ALEX KUSHNER GENERAL INC

Agency

City of Fremont, CA

Contract Type

CONSTRUCTION

Document Date

April 14, 2026

Renewal Info

Amendment increases contract funding by $80,000 for additional work, establishing a new not-to-exceed total of $1,032,200 for the existing construction contract.

More from ALEX KUSHNER GENERAL INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free