Lift Station Rehab Equipment Contract Awarded to Emery & Sons
Trusted by teams at
Description
Astoria City Council approved a $1,199,207.70 contract amendment with Emery & Sons Construction Group for early procurement of screw pumps and sluice gates for the Sewage Lift Stations Rehabilitation Project. The amendment secures critical equipment to maintain project schedule.
Contract Details
Contract Amount
$1,199,207.70
Vendor
EMERY & SONS CONSTRUCTION GROUP LLC
Agency
Town of Astoria, IL
Contract Type
CONSTRUCTION
Document Date
June 1, 2026
Renewal Info
Early work package is an amendment to the principal construction contract. Previous approvals included pre-construction fees; this amendment focuses on major equipment purchase. Further contract amendments for installation and construction likely as project advances.
More from EMERY & SONS CONSTRUCTION GROUP LLC
More from Town of Astoria
Astoria City Council Agenda 2026-06-02
Astoria City Council Agenda Packet 2026-06-02
Astoria City Council AgendaPacket 2026-06-01
Astoria City Council AgendaPacket 2026-06-01
Astoria City Council AgendaPacket 2026-06-01
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.