CONSTRUCTIONAMENDED

SFPUC 2025 Resolution Log December 2025

Mountain Tunnel Contract Decreased and Contingency Raised

Decrease $15,727,083 (new total $132,876,212); contingency increase $13,029,702 (now $17,296,914); limit $150,173,126San Francisco Public Utilities CommissionMOUNTAIN TUNNEL CONSTRUCTORS INCDecember 10, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

SFPUC amended its Mountain Tunnel contract, reducing costs by $15.7 million, adjusting project scope, and increasing the contingency for new repairs.

Contract Details

Contract Amount

Decrease $15,727,083 (new total $132,876,212); contingency increase $13,029,702 (now $17,296,914); limit $150,173,126

Vendor

MOUNTAIN TUNNEL CONSTRUCTORS INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

December 10, 2025

Contract Term

No change to duration

Renewal Info

Decrease in contract value, contingency adjustment, no term change.

More from MOUNTAIN TUNNEL CONSTRUCTORS INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free