San Francisco Public Utilities Commission Resolution Log 2026-05-27

Mountain Tunnel Improvements Budget Increased to $165M

Increase of $15,000,000 for a revised cost limit of $165,173,126San Francisco Public Utilities CommissionMOUNTAIN TUNNEL CONSTRUCTORS INCMay 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The SFPUC increased the cost contingency for the Mountain Tunnel Improvements Contract HH-1000R with Mountain Tunnel Constructors, Inc. by $15 million, raising the cost limit to $165,173,126 to address schedule-related and scope changes.

Contract Details

Contract Amount

Increase of $15,000,000 for a revised cost limit of $165,173,126

Vendor

MOUNTAIN TUNNEL CONSTRUCTORS INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

May 27, 2026

Contract Term

No change to contract duration limit

Renewal Info

Existing cost contingency increased by $15,000,000; duration limit unchanged.

More from MOUNTAIN TUNNEL CONSTRUCTORS INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free