Sewer Project Change Order For DeVincentis Tabled
Trusted by teams at
Description
Barton & Loguidice prepared Change Order No. 6 for contractor G. DeVincentis & Son Construction Co., Inc. on the Sanitary Sewer Pump Station and Force Main Improvements project, adding $16,889.36 for unforeseen work at O’Sheas Pump Station. The Board tabled the resolution authorizing the change order pending additional engineering documentation.
Contract Details
Contract Amount
$16,889.36 (change order increase; new total $8,006,938.19)
Vendor
G DEVINCENTIS & SON CONSTRUCTION CO INC
Agency
Town of Chenango, NY
Contract Type
CONSTRUCTION
Document Date
April 29, 2026
Contract Term
Contract Substantial Completion 720 days (February 11, 2026); Ready for Final Payment 60 days (April 12, 2026); no time change with CO 06
Renewal Date
2026-04-12
Renewal Info
Change Order No. 06 increases the contract price but does not modify the substantial completion or final payment dates. Prior approved change orders resulted in a net decrease of $271,048.33 from the original contract before this change.
More from G DEVINCENTIS & SON CONSTRUCTION CO INC
More from Town of Chenango
Town of Chenango Town Board AgendaPacket 2026-06-24
Town of Chenango Town Board AgendaPacket 2026-06-24
Town of Chenango Town Board AgendaPacket 2026-06-24
Town of Chenango Town Board AgendaPacket 2026-06-24
Town of Chenango Agenda Packet 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.