Town of Chenango Board Agenda May 2024

$246,000 Change Order for Sewer Project Approved

Change order increase $246,000.00; total new contract $7,981,000.00Town of ChenangoG DEVINCENTIS & SON CONSTRUCTION CO INCMay 15, 2024

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Town of Chenango approved a $246,000 change order to G. DeVincentis & Son Construction Co., Inc., bringing their wastewater sewer contract total to $7,981,000 for additional pump station work. The change order was effective May 1, 2024.

Contract Details

Contract Amount

Change order increase $246,000.00; total new contract $7,981,000.00

Vendor

G DEVINCENTIS & SON CONSTRUCTION CO INC

Agency

Town of Chenango, NY

Contract Type

CONSTRUCTION

Document Date

May 15, 2024

Contract Term

Substantial Completion: 720 days (Feb 11, 2026); Final Payment: 60 days (April 12, 2026)

Renewal Date

2026-04-12

Renewal Info

Change Order No. 2 amends scope and increases contract amount. Contract schedule unchanged; substantial completion to remain February 11, 2026. No extension of time granted.