South Dakota Transportation Commission Meeting Minutes 2026-04-23

US 385 Reconstruction Contract Increased for Slope Stability Work

Original $49,081,403.60; CCO No. 9 change $572,935.90; net change to date $1,361,937.78South Dakota Department of Transportation | Transportation CommissionOFTEDAL CONSTRUCTION INCApril 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The major US 385 reconstruction project with Oftedal Construction Inc. increased by $572,935.90 in CCO No. 9 to address additional clearing and excavation for slope stability. Net changes have boosted the original $49.08 million contract by $1.36 million.

Contract Details

Contract Amount

Original $49,081,403.60; CCO No. 9 change $572,935.90; net change to date $1,361,937.78

Vendor

OFTEDAL CONSTRUCTION INC

Agency

South Dakota Department of Transportation | Transportation Commission, SD

Contract Type

CONSTRUCTION

Document Date

April 23, 2026

Renewal Info

Ninth change order adds slope stability work; cumulative contract increases represent about 2.8% over the original bid.

More from OFTEDAL CONSTRUCTION INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free