I-229 Exit 4 Contract Reduced via Dowel Bar Adjustment
Trusted by teams at
Description
South Dakota DOT approved Change Order No. 8 with T & R Contracting, Inc. for the I-229 Exit 4 project, decreasing the contract by $173,415.59 after correcting an overestimated dowel bar quantity. The amendment reduces the overall increase while maintaining a positive net change on the $48 million contract.
Contract Details
Contract Amount
$(173,415.59) (change on CCO No. 8); original contract $48,026,131.12; net change to date $506,556.47
Vendor
T & R CONTRACTING INC
Agency
South Dakota Department of Transportation | Transportation Commission, SD
Contract Type
CONSTRUCTION
Document Date
May 18, 2026
Renewal Info
Change Order No. 8 corrects an estimated dowel bar quantity error, reducing the contract value while keeping all other terms in place.
More from T & R CONTRACTING INC
Issuing Agency
State
Pierre, SD
More from South Dakota Department of Transportation | Transportation Commission
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.