Basin Construction wins SD20 inslope and riprap project
Trusted by teams at
Description
Basin Construction & Drain Tile, LLC submitted the low bid of $762,625.50 for inslope repair and riprap work on SD20 in Spink County. The project must be completed by October 30, 2026 and is below the engineer's estimate.
Contract Details
Contract Amount
$762,625.50
Vendor
BASIN CONSTRUCTION & DRAIN TILE LLC
Agency
South Dakota Department of Transportation | Transportation Commission, SD
Contract Type
CONSTRUCTION
Document Date
April 1, 2026
Contract Term
Through 10/30/2026 (contract time for Project PT 0020(228)326)
Renewal Date
2026-10-30
Renewal Info
Construction contract for Project PT 0020(228)326 with completion by 10/30/2026; renewal terms not provided.
More from BASIN CONSTRUCTION & DRAIN TILE LLC
Issuing Agency
State
Pierre, SD
More from South Dakota Department of Transportation | Transportation Commission
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
South Dakota Department of Transportation Construction Change Orders Report 2026-05-18
Get alerts on contract renewals, new awards, and vendor activity.
B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.