City of Marathon Resolution 2026-42 Sombrero Blvd Drainage Improvements Change Order #4

Marathon approves Change Order #4 for Sombrero Blvd project

Option 1: $57,038.16; Option 2: $266,225.88 (Change Order #4 to original contract price $4,870,496.00, current price $5,023,550.51)City of MarathonCHARLEY TOPPINO & SONS INCMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Marathon approved Change Order #4 with Charley Toppino & Sons, Inc. for the Sombrero Blvd Drainage Improvements Project, adding either $57,038.16 (Option 1) or $266,225.88 (Option 2) in construction work. The amendment covers additional pipe support, driveway and intersection asphalt reconstruction, and optionally a project-wide asphalt leveling course without extending the 470-day contract term.

Contract Details

Contract Amount

Option 1: $57,038.16; Option 2: $266,225.88 (Change Order #4 to original contract price $4,870,496.00, current price $5,023,550.51)

Vendor

CHARLEY TOPPINO & SONS INC

Agency

City of Marathon, FL

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Contract Term

No change in contract time; current contract time 470 days, substantial completion May 31, 2026

Renewal Date

2026-05-31

Renewal Info

Change Order #4 is an amendment increasing the contract price by either $57,038.16 (new total $5,080,588.67) or $266,225.88 (new total $5,289,776.39) with no additional contract days; substantial completion remains May 31, 2026. Previous Change Orders #1–#3 increased the price by $210,092.67 and extended time by 105 days.