Approval of change orders for the Western Sewer Project, including additional rock excavation, Patterson Drive tunnel work, and plug valves. This project involves the rehabilitation of an existing sewer line to reduce inflow and infiltration within the Marlowe Creek sewer shed.

Change Order 1 for $2,010 was previously executed. Change Orders 5 and 6 are anticipated for the Jun...

City of RoxboroWestern Sewer Project Change Orders 2-4 Approval

Why this matters for vendors

Early signals like this typically surface 6–18 months before a formal RFP is posted. Vendors who engage during the planning window help shape requirements, build relationships with decision-makers, and position ahead of the competition before the solicitation goes public.

Public Works

Where this sits in the buying cycle

Now

Capital plan & early discussion

Next 1–2 Q

Scoping & vendor outreach window

6–18 mo

RFP / solicitation posted

Later

Award & contract

Related

Similar signals forming now

Opportunities from other agencies that match this category and scope.

Pre-RFP

The Marblehead Board of Health is rolling out Town-issued trash and recycling carts and shifting to automated curbside collection in most areas by July 1, 2026. All trash and recycling must be placed in Town-issued carts, with items outside the carts no longer collected, and residents are instructed to contact the Health Department if carts are damaged. This change implies that Marblehead either has or will maintain contracts for supplying standardized carts, automated-compatible collection vehicles, and related services, alongside ongoing support for cart repair/replacement logistics. Vendors in solid waste collection, cart supply, route optimization, and customer service systems can position themselves for future needs such as additional cart orders, replacements, technology to manage cart inventory, and potential expansions or adjustments to the automated collection program.

Program details and regulations are managed through the Health Department and Board of Health; carts...

Town of Marblehead
View signal
Budget Planning

The Storm Drain Maintenance & Rehabilitation Program in Tiburon’s adopted FY 2026‑27 CIP funds $1.075 million in 2026‑27 and $2.775 million over five years for drainage projects, including an annual storm drain lining program, Railroad Marsh stormwater basin maintenance, Taylor Road Drainage Improvements, and ongoing design for future projects. The lining project alone has a five‑year cost of $1.9 million, and the design component is funded at $75,000 per year to plan future rehabilitations, all funded primarily from the Streets & Drainage and Drainage Impact funds. No specific engineering or construction vendors are named, and several projects are described as ongoing or to be designed. Drainage and stormwater engineering firms, as well as trenchless lining contractors, can help Tiburon prioritize failing assets, design rehabilitation projects, and deliver annual and one‑off capital drainage work under this program.

Specific sub‑projects include annual pipe lining, Railroad Marsh basin maintenance, and Taylor Road ...

Town of Tiburon
View signal
Pre-RFP

The Storm Drain Maintenance & Rehabilitation Program lists several FY 2026‑27 projects: a $500,000 annual storm drain lining project, $350,000 for Railroad Marsh stormwater retention basin maintenance, $75,000 for storm drain project design, and $150,000 for Taylor Road drainage improvements, totaling $1,075,000. Over five years, storm drain projects are funded at $2.775 million, mainly from the General Fund Streets & Drainage and the Drainage Impact Fund. The budget describes these as design and construction efforts but does not identify existing contractors, suggesting that detailed design, condition assessment, and construction contracts are still to be defined. Civil/environmental engineering firms and underground contractors can propose lining methods, basin rehab strategies, and localized drainage solutions, especially for Taylor Road and the Railroad Marsh facility, and help the town package these into competitive bids.

Railroad Marsh stormwater basin work ties into the separate Marsh Restoration Fund and open space/we...

Town of Tiburon
View signal

Get alerts for similar opportunities

Get automatic alerts for signals in your industry — months before they become formal RFPs. No more searching.

Get Early Alerts

Platform Capabilities

How Civic IQ accelerates your sales

Uncover early buying signals, get real-time alerts, and push context-rich leads straight into your CRM.

Spot Demand Early

Detect the first hints of need in agendas, budgets, and strategic plans up to a year before formal procurement begins.

Real-Time Alerts & CRM Sync

Receive instant notifications and automatically enrich records in your connected CRM, keeping your pipeline current.

Connect with Stakeholders

Get current contact and contract details to reach the person running the project now, not someone who left months ago.

Monitor Competitors

Track competitor wins, contract expirations, and renewal timelines so you can perfectly time outreach.

1M+

Documents analyzed monthly

8M+

Vendors tracked

22M+

Documents indexed

24h

Max data refresh cycle

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free