CONSTRUCTIONONGOING

Waucondah WWTP Phase 2 construction payments to Moltz

Moltz Construction, Inc. continues work on the Waucondah Wastewater Treatment Plant Phase 2 improvements, with an August 19, 2026 capital payment of $528,176.78. Engineering review of Payment Application #8 shows the project is approximately 57% complete with half of contract time consumed.

Status
ONGOING
Document date
August 19, 2026
Contract type
CONSTRUCTION
Vendor
Moltz Construction Inc
Agency
Perry Park Water & Sanitation District · CO

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$528,176.78 (August 19, 2026 payment application)
Contract type
CONSTRUCTION
Contract term
Project schedule ongoing in 2026; contract time consumed to date 50%, completion 57% as of Payment Application #8
Renewal
Construction contract is progressing under Payment Application #8; no explicit renewal but ongoing until substantial and final completion as per project schedule.
Document type
Agenda
Source document
Perry Park Water and Sanitation District Agenda 2026-08-19

Related contracts

Other contracts from Moltz Construction Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Perry Park Water & Sanitation District?

Moltz Construction Inc was awarded this construction contract by Perry Park Water & Sanitation District, as recorded on August 19, 2026. The contract value is $528,176.78 (August 19, 2026 payment application).

How much is the Moltz Construction Inc contract with Perry Park Water & Sanitation District worth?

The Moltz Construction Inc contract with Perry Park Water & Sanitation District is valued at $528,176.78 (August 19, 2026 payment application), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Perry Park Water and Sanitation District Agenda 2026-08-19 (Agenda), dated August 19, 2026 from Perry Park Water & Sanitation District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Moltz Construction Inc hold?

Moltz Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Moltz Construction Inc's profile

What is Perry Park Water & Sanitation District currently buying?

Explore Perry Park Water & Sanitation District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Perry Park Water & Sanitation District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free