CONSTRUCTIONAMENDED

ODP Change Order Reduces EOTO Clinic GMP

The School District of Osceola County is approving Change Order No. 1 with Bishop Construction Group, Inc. for the EOTO Clinic Portables Fit-Out project, implementing a $125,514.12 deductive Owner Direct Purchasing change. The amendment decreases the GMP from $1,353,304.55 to $1,227,790.43 while maintaining the original completion dates to capture sales tax savings on materials.

Status
AMENDED
Document date
April 21, 2026
Contract type
CONSTRUCTION
Vendor
Bishop Construction Group Inc
Agency
Osceola County School District · FL

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Decrease in the amount of ($125,514.12); original GMP $1,353,304.55 reduced to $1,227,790.43; overall contract sum $1,360,120.07
Contract type
CONSTRUCTION
Contract term
Original contract date April 21, 2026; Substantial Completion August 7, 2026; Final Completion October 9, 2026
Renewal date
2026-10-09
Renewal
Change Order No. 1 is a deductive amendment under the Owner Direct Purchasing Program, reducing the GMP by $125,514.12 without extending the contract time. Future sales tax savings from direct material purchases will be reconciled at project closeout; no renewal options are specified.
Document type
Agenda
Source document
School District of Osceola County Agenda Change Order Approval 2026-04-21

Related contracts

Other contracts from Bishop Construction Group Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Osceola County School District?

Bishop Construction Group Inc was awarded this construction contract by Osceola County School District, as recorded on April 21, 2026. The contract value is Decrease in the amount of ($125,514.12); original GMP $1,353,304.55 reduced to $1,227,790.43; overall contract sum $1,360,120.07.

How much is the Bishop Construction Group Inc contract with Osceola County School District worth?

The Bishop Construction Group Inc contract with Osceola County School District is valued at Decrease in the amount of ($125,514.12); original GMP $1,353,304.55 reduced to $1,227,790.43; overall contract sum $1,360,120.07, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in School District of Osceola County Agenda Change Order Approval 2026-04-21 (Agenda), dated April 21, 2026 from Osceola County School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Bishop Construction Group Inc hold?

Bishop Construction Group Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Bishop Construction Group Inc's profile

What is Osceola County School District currently buying?

Explore Osceola County School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Osceola County School District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free