City of Pasco Council Meeting Agenda April 2026

Lewis Street Overpass Final Change Order Credits City Funds

Approximately -$710,000 (credit change order)Pasco Public Facilities DistrictCASCADE BRIDGE LLCApril 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Pasco City Council approved Resolution No. 4722, authorizing Change Order No. 58 with Cascade Bridge, LLC as the final reconciliation for the Lewis Street Overpass Project. The closing change order provides a credit of about $710,000 back to the City due to lower actual quantities than originally estimated.

Contract Details

Contract Amount

Approximately -$710,000 (credit change order)

Vendor

CASCADE BRIDGE LLC

Agency

Pasco Public Facilities District, WA

Contract Type

CONSTRUCTION

Document Date

April 20, 2026

Renewal Info

Final reconciliation change order (No. 58) to the Lewis Street Overpass construction contract; marks project closeout with no further amendments anticipated.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free