CONSTRUCTIONAMENDED

City of Washington Council Meeting Agenda March 2025

Earth Crest Bridge Project Amended for Cost Savings

Original Contract Price $1,259,570.65; Change Order #1 -$150,000; New Contract Amount $1,109,570.65; Projected Overall Cost $1,051,788.65City of WashingtonK.J. UNNERSTALL CONSTRUCTION COMarch 17, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Washington approved Change Order #1 with K.J. Unnerstall Construction Co. for the 2024 Earth Crest Extension Bridge Project, amending the contract to a new total of $1,109,570.65 and accepting substantial value engineering changes that lower the city's cost by $150,000, resulting in a revised project scope using a box culvert.

Contract Details

Contract Amount

Original Contract Price $1,259,570.65; Change Order #1 -$150,000; New Contract Amount $1,109,570.65; Projected Overall Cost $1,051,788.65

Vendor

K.J. UNNERSTALL CONSTRUCTION CO

Agency

City of Washington, MO

Contract Type

CONSTRUCTION

Document Date

March 17, 2025

Renewal Info

Amendment includes value engineering design; projected overall cost reduced. Future mitigation costs beyond $25,000 covered by city. No explicit renewal. Contract amended March 2025.

More from K.J. UNNERSTALL CONSTRUCTION CO

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free