Civic IQ
CONSTRUCTIONAMENDED

Town of Silverthorne Council Meeting Agenda March 2026

Amended Pavilion Bridge ADA Ramp Contract with Columbine Hills Construction

$1,209,441.75Town of SilverthorneCOLUMBINE HILLS CONSTRUCTION LLCMarch 25, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Town Council amended the ADA Ramp at Pavilion Bridge contract with Columbine Hills Construction LLC, increasing the amount to $1,209,441.75 to complete the full original scope. Work must reach substantial completion by October 31, 2026 and be finished by November 30, 2026.

Contract Details

Contract Amount

$1,209,441.75

Vendor

COLUMBINE HILLS CONSTRUCTION LLC

Agency

Town of Silverthorne, CO

Contract Type

CONSTRUCTION

Document Date

March 25, 2026

Contract Term

Substantially complete by October 31, 2026; final payment by November 30, 2026

Renewal Date

2026-11-30

Renewal Info

Contract originally approved March 11, 2026 for $921,575.25 and amended March 25, 2026 with a $287,866.50 change order to complete full project scope. End date extended to November 30, 2026.