Rodan Builders Change Order 4 Adds Cost and Time
Trusted by teams at
Description
The Board is asked to approve Change Order No. 4 with Rodan Builders for $202,035.00 and a 77-day extension on the Men's Locker Room Demolition project at San Jose City College, increasing the total contract to $4,190,192.00. The amendment addresses accessibility upgrades and additional code-driven work.
Contract Details
Contract Amount
$202,035.00 (Revised total contract $4,190,192.00)
Vendor
RODAN BUILDERS
Agency
San Jose-Evergreen Community College District, CA
Contract Type
CONSTRUCTION
Document Date
May 12, 2026
Contract Term
Contract completion date extended by 77 calendar days
Renewal Info
Fourth change order to the July 8, 2025 contract; cumulative change now 19.79% over original value with a 77-day schedule extension.
More from RODAN BUILDERS
More from San Jose-Evergreen Community College District
San Jose-Evergreen Community College District Board Meeting Agenda May 2026
San Jose-Evergreen Community College District Board Meeting Agenda May 2026
San Jose-Evergreen Community College District Board Meeting Agenda May 2026
San Jose-Evergreen Community College District Board Meeting Agenda May 2026
San Jose-Evergreen Community College District Board Meeting Agenda May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.